Meeting the Defence housing requirement

Objectives

Key performance indicator  2011–12 target 2011–12 achievement
% ADF member satisfaction with house 80% 90%
Stock provisioned for client against
agreed provisioning plan
>95% 101%

Major outcomes

  1. Provided a total portfolio of 17,471 houses for Defence families (Members With Dependants) in accordance with the agreed provisioning schedule.
  2. Constructed or purchased 704 new houses for Defence families.
  3. Acquired the Warner Springs site for Defence housing in the Brisbane suburb of Brendale.
  4. Referred development of Rasmussen, Townsville; Lindfield, Ermington and Kellyville in Sydney; and Weston Creek in Canberra to the Parliamentary Standing Committee on Public Works (PWC).
  5. Acquired housing by construction or purchase for the relocation of 3RAR from Sydney to Townsville.
  6. Handed over the first 29 completed houses on Larrakeyah Barracks, Darwin with the balance of 68 to be completed during 2012–13.
  7. Completed Stage 1 civil works, initiated Stage 2 civil works and started construction of 50 Defence houses in Stage 1 at Muirhead, Darwin.
  8. Completed the Defence-funded air conditioning project which, over three years, addressed the air conditioning needs of 3,500 DHA managed properties at a cost of $23.3 million.
Defence housing requirement